Part 2 · Before You Start Planning

Question 2

Which of these statements about Working Times (base) Calendars is incorrect?

  1. A Project Calendar (Standard by default) stipulates which days are working and non-working days.
  2. There can be several base calendars in a project plan.
  3. Different days of the week can have different start and finish times.
  4. The Project Calendar (Standard by default) stipulates to MS Project how many hours there are in a day and a week.

Answer: CorrectIncorrect

No, the projects calendar does stipulate which days are working days and non-working days. Although an individual resource can have exceptions to this calendar.

No, a project can have multiple base calendars (although it can only have one project calendar). Base calendars can be defined for different countries and for shift and part-time workers.

No, the project calendar can infact be set to have different start and finish times for different days, it can aslo be set for longer or shorter days. But, it is recommended that things are kept simple and the project calendar is set to a flat working week with the same start and finish times for Monday to Friday.

Workings Times (base) Calendars do not determine how many hours there are in a day and a week. It is the calendar options (Tools, Options, Calendar tab) that set the number of hours in the day and hours in a week.