Part 3 · Creating the Schedule

Question 1

Which of the following is not a quality of the Project Summary Task?

  1. It is a summary of the entire project.
  2. It is a Top Level Task.
  3. It is given the number zero in the task list.
  4. It is displayed on the Gantt Chart as a grey summary bar.

Answer: CorrectIncorrect

The Project Summary Task does summarise the entire project in one line. It gives information on the projects start and finish dates, overall duration, cost etc.
Note that the question asks which is not a property of the Project Summary task.

The Project summary task is not a top level task. MS Project classes it as above the breakdown structure. Any task that is in the projects first breakdown level is classed as a top level task (outline level 1).

Question 2

The Project Summary Task is assigned the ID number of zero to distinguish it from all other tasks.
Note that the question asks which is not a property of the Project Summary task.

To highlight the Project Summary Task its task bar is shown in grey in the Gantt chart.
Note that the question asks which is not a property of the Project Summary task.