Part 3 · Creating the Schedule
Answer: CorrectIncorrect
The manual entry of a task start date is the technique of the novice
project user. This technique ignores the fact that tasks are dependent upon each other,
it can cause many headaches when the project has to be rescheduled in any way.
Task links should be used to schedule tasks, but lead and lag
times should only be used in their appropriate places. They should be used to model
over lapping tasks and waiting periods.
A "Must Start On" constraint locks a task so it must begin on that day in
the schedule. The nature of a project means a task's planned start date will
often change as the schedule is developed. It is far better to schedule tasks
using task dependencies and use the default constraint - "As Soon As Possible".
Whenever possible tasks should be scheduled with dependencies.
