Part 4 · Resourcing and Costing the Project

Question 3

With MS Project in its default, out of the box, settings. What will happen to a 2 day (16 hr) task when its resources units are lowered from 100% to 50%?

  1. Nothing.  Resource units cannot be changed once they have been assigned.
  2. The task will have a duration of 4 days with 16 hours work.
  3. The task will have a duration of 4 days with 32 hours work.
  4. The task will have a duration of 2 days with 8 hours work.

Answer: CorrectIncorrect

The resource units assigned to a task can be changed at any time.

Under its default settings, Project keeps the work value the same when resource units are changed.  This means the duration of the task must change.  In this case the halving of resource units will double the duration of the task.

Question 4

With the resource allocation halving, the duration will double to 4 days.  But the resource will only be working 50% of each day so the work will not be 32 hours (four eight hour days).

Under the default settings, Project keeps the work value fixed when resource units are changed rather than the duration.  Settings can be changed to fix the duration and when this is done Project will respond in the way outlined in answer D.