Part 4 · Resourcing and Costing the Project

Question 5

With MS Project in its default, out of the box, settings.  Bob has been assigned to a 4 day task (32 hours work).  Clare is then assigned to the task.  The task becomes...

  1. A 4 day task with a total of 64 hours work (Bob & Clare - 32 hours each).
  2. A 4 day task with a total of 32 hours work (Bob & Clare - 16 hours each).
  3. A 2 day task with a total of 32 hours work (Bob & Clare - 16 hours each).
  4. A 2 day task with 32 hours (all Bob as a second resource cannot be assigned in this way).

Answer: CorrectIncorrect

This is how Project behaved prior to Project 98.  A change of settings will make it behave in this way again.  But, by default, the adding of an extra resource reduces the duration of a task rather than increasing the work.

By default the adding of extra resources reduces the duration of a task rather than sharing the work between the resources.

Project's settings can be changed to make it perform calculations in the manner of this answer.

The adding of a resource increases the overall allocation on a the task, thus the task duration will reduce and the work is split between the resources.

Part 5

You can assign as many different resources to a task as required.  But an understanding of the effect of adding resources is necessary before you attempt to do this.