Part 4 · Resourcing and Costing the Project
Answer: CorrectIncorrect
This is how Project behaved prior to Project 98. A change of settings will make it behave in this way again. But, by default, the adding of an extra resource reduces the duration of a task rather than increasing the work.
By default the adding of extra resources reduces the duration of a task rather than sharing the work between the resources.
Project's settings can be changed to make it perform calculations in the manner of this answer.
The adding of a resource increases the overall allocation on a the task, thus the task duration will reduce and the work is split between the resources.
You can assign as many different resources to a task as required. But an understanding of the effect of adding resources is necessary before you attempt to do this.