Part 5 · Evaluation and Baselining
Answer: CorrectIncorrect
This is the incorrect statement and thus the right answer. The Critical Path determines the length of the project. But a change to a task on or nearly on the critical path may shorten or lengthen the Critical Path. Therefore a project can always be completed in a shorter time than the critical path if activities perform better than originally estimated.
No. The Critcal Path is the longest path through a project.
No. The Critical Path does determine the schedule finish date of the project.
No. Tasks with zero Slack are always classed as critical.