Part 5 · Evaluation and Baselining
Answer: CorrectIncorrect
1) The Detail Gantt clearly shows critical tasks in red with slack bars on non critical bars.
2) The Network Diagram in Project 2000 highlights the Critical Path in red but usually needs some work on the layout, to make the Critcal Path clear.
3) The Gantt chart does not show details of criticality or slack but can be formatted to do so using the Gantt chart wizard.
4) The Resource sheet does not show any tasks and thus no Critical Path.
You have not entered the optimum order, press reset and try again