Part 5 · Evaluation and Baselining
Answer: CorrectIncorrect
The Leveling Gantt does not show resource allocations and thus on its own is not suitable for resource leveling.
The Resource Graph shows when resources allocations occur but does not show the tasks which are carrying the allocations.
The Resource Sheet shows which resources are allocated, but not when or how.
The Resource Allocation view is a combination view that shows which resources are over-allocated, when an over-allocation occurs and the tasks that cause the scheduling problem.