No, all tasks should be scheduled ASAP, critical or not.
Yes, wherever possible all tasks in the project should be scheduled to start as soon as possible.
No, all tasks should be ASAP as all other settings cause problems when performing critical path analysis.
No, all tasks should be ASAP as all other settings cause problems when performing critical path analysis.