Part 5 · Evaluation and Baselining
Answer: CorrectIncorrect
No, stakeholders must give their commitment to the plan prior to baselining.
No, the actual cost of the project is not known until the project is completed. At this stage we only know the planned cost.
It is very important to have a baseline for reference during tacking and management of the project.
The plan can still be changed once a baseline has been saved. But a saved baseline would highlight changes made by management.