Logo

TRINITY PROJECTS

Microsoft Project Quiz

Part 5 · Evaluation and Baselining

Question 5

Why is it necessary to save a baseline?

  1. To freeze the plan so stakeholders can give their commitment to it.
  2. To freeze the plan so the actual cost of the project is known.
  3. To freeze the plan at the end of the planning phase so it can be used as a reference while tracking and managing the project.
  4. To stop management making changes to the plan.

Answer: CorrectIncorrect

No, stakeholders must give their commitment to the plan prior to baselining.

No, the actual cost of the project is not known until the project is completed. At this stage we only know the planned cost.

It is very important to have a baseline for reference during tacking and management of the project.

Part 6

The plan can still be changed once a baseline has been saved. But a saved baseline would highlight changes made by management.