Part 6 · Management and Tracking of the Project
Answer: CorrectIncorrect
This system can work well but only if the tasks are small and updates are only required when a task is complete.
The entering of percentage complete values is not recommended as resources claim to be 90% complete very quickly, but then take a long time to reach 100%. Try to stick to entering actual durations and estimates of the remaining duration.
These buttons make the assumption that the task is completing exactly as scheduled, this is a dangerous assumption to make.
Yes, the Update Tasks form allows you to enter the key information on the progress of a task in one go. This is the ideal way of tracking actuals.