Part 6 · Management and Tracking of the Project
Answer: CorrectIncorrect
Project will always produce a result that makes mathematical sense. This means it will reject the assumption that you are 95% complete with 7 days done and still 3 remaining.
Project will always produce a result that makes mathematical sense. When all three values are entered it rejects the %Complete and calculates this value from the actual and remaining values entered.
Project will always produce a result that makes mathematical sense. When all three values are entered and they do not add up, the actual and remaining values take preference over the %complete. In this answer the %complete and the remaining are causing a recalculation of the actual as well as the duration of the task.
Project will always produce a result that makes mathematical sense. When all three values are entered and they do not add up, the actual and remaining values take preference over the %complete. In this answer the %complete and the actual are causing a recalculation of the remaining as well as the duration of the task.
Project will always produce a result that makes mathematical sense. When all three values are entered and they do not add up the actual and remaining values take preference over the %complete. In this answer the %complete and the remaining are causing a recalculation of the actual as well as the duration of the task.