Part 6 · Management and Tracking of the Project
Answer: CorrectIncorrect
All of the measures can be employed when the project starts to slip, but care must be taken with some of these. De-scoping the project can reduce the quality of the project, which the client may not accept. Overtime, on the other hand may increase the project costs, which will start to eat away at your profits.