| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 0 | Moving Office | 30 d | 24/07/02 | 04/09/02 | 24% | |
| 1 | Project Start | 0 d | 24/07/02 | 24/07/02 | 100% | |
| 2 | Pre Access Activity | 5 d | 24/07/02 | 30/07/02 | 100% | |
| 3 | Arrange Lease | 5 d | 24/07/02 | 30/07/02 | Company Secretary | 100% |
| 4 | Pre Move Activity | 21 d | 31/07/02 | 29/08/02 | 17% | |
| 5 | Clean Office | 5.6 d | 31/07/02 | 07/08/02 | Direct Labour[500%] | 50% |
| 6 | Decorate | 11 d | 02/08/02 | 19/08/02 | Decorating Contractor | 0% |
| 7 | Measure Office | 1 d | 31/07/02 | 31/07/02 | Office Manager | 100% |
| 8 | Plan Fittings | 3 d | 01/08/02 | 05/08/02 | Office Manager | 75% |
| 9 | Order Fittings | 1 hr | 06/08/02 | 06/08/02 | Office Manager | 0% |
| 10 | Fittings Delivered | 0 d | 15/08/02 | 15/08/02 | 0% | |
| 11 | Install Fittings | 5.6 d | 19/08/02 | 28/08/02 | Direct Labour[500%] | 0% |
| 12 | Plan Furniture | 3 d | 06/08/02 | 09/08/02 | Office Manager | 0% |
| 13 | Order Furniture | 1 hr | 09/08/02 | 09/08/02 | Office Manager | 0% |
| 14 | Furniture Delivered | 0 d | 20/08/02 | 20/08/02 | 0% | |
| 15 | Install Furniture | 1 d | 28/08/02 | 29/08/02 | Direct Labour[500%] | 0% |
| 16 | Recruit Staff | 4 d | 31/07/02 | 19/08/02 | Human Resources | 25% |
| 17 | Train Staff | 7 d | 20/08/02 | 29/08/02 | Human Resources | 0% |
| 18 | Moving Acivity | 4 d | 30/08/02 | 04/09/02 | 0% | |
| 19 | Move in | 4 d | 30/08/02 | 04/09/02 | Direct Labour[500%] | 0% |
| 20 | Project Complete | 0 d | 04/09/02 | 04/09/02 | 0% |
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 3 | Arrange Lease | Company Secretary | 35 hrs | 24/07/02 | 30/07/02 | 100% |
| 5 | Clean Office | Direct Labour | 196 hrs | 31/07/02 | 07/08/02 | 50% |
| 6 | Decorate | Decorating Contractor | 77 hrs | 02/08/02 | 19/08/02 | 0% |
| 7 | Measure Office | Office Manager | 7 hrs | 31/07/02 | 31/07/02 | 100% |
| 8 | Plan Fittings | Office Manager | 21 hrs | 01/08/02 | 05/08/02 | 75% |
| 9 | Order Fittings | Office Manager | 1 hr | 06/08/02 | 06/08/02 | 0% |
| 11 | Install Fittings | Direct Labour | 196 hrs | 19/08/02 | 28/08/02 | 0% |
| 12 | Plan Furniture | Office Manager | 21 hrs | 06/08/02 | 09/08/02 | 0% |
| 13 | Order Furniture | Office Manager | 1 hr | 09/08/02 | 09/08/02 | 0% |
| 15 | Install Furniture | Direct Labour | 35 hrs | 28/08/02 | 29/08/02 | 0% |
| 16 | Recruit Staff | Human Resources | 26 hrs | 31/07/02 | 19/08/02 | 27% |
| 17 | Train Staff | Human Resources | 49 hrs | 20/08/02 | 29/08/02 | 0% |
| 19 | Move in | Direct Labour | 140 hrs | 30/08/02 | 04/09/02 | 0% |