Moving Office

Project Start: 24/07/02 — Project Finish: 04/09/02

Image

Microsoft Project Image

Tasks

ID
Task Name
DurationStartFinishResource Names% Complete
0
Moving Office
30 d24/07/0204/09/02 24%
1
Project Start
0 d24/07/0224/07/02 100%
2
Pre Access Activity
5 d24/07/0230/07/02 100%
3
Arrange Lease
5 d24/07/0230/07/02Company Secretary100%
4
Pre Move Activity
21 d31/07/0229/08/02 17%
5
Clean Office
5.6 d31/07/0207/08/02Direct Labour[500%]50%
6
Decorate
11 d02/08/0219/08/02Decorating Contractor0%
7
Measure Office
1 d31/07/0231/07/02Office Manager100%
8
Plan Fittings
3 d01/08/0205/08/02Office Manager75%
9
Order Fittings
1 hr06/08/0206/08/02Office Manager0%
10
Fittings Delivered
0 d15/08/0215/08/02 0%
11
Install Fittings
5.6 d19/08/0228/08/02Direct Labour[500%]0%
12
Plan Furniture
3 d06/08/0209/08/02Office Manager0%
13
Order Furniture
1 hr09/08/0209/08/02Office Manager0%
14
Furniture Delivered
0 d20/08/0220/08/02 0%
15
Install Furniture
1 d28/08/0229/08/02Direct Labour[500%]0%
16
Recruit Staff
4 d31/07/0219/08/02Human Resources25%
17
Train Staff
7 d20/08/0229/08/02Human Resources0%
18
Moving Acivity
4 d30/08/0204/09/02 0%
19
Move in
4 d30/08/0204/09/02Direct Labour[500%]0%
20
Project Complete
0 d04/09/0204/09/02 0%

Resources

IDNameGroupMax UnitsPeak Units
1Company Secretary 100%0%
2Office Manager 100%100%
3Sales Manager 100%0%
4Direct Labour 500%500%
5Decorating Contractor 100%100%
6Human Resources 100%100%

Assignments